Project Stats

Category:

Structural

Contract Amount:

$3,100,000.00

Contract Type:

Subcontractor

General Contractor:

Sippel Steel Fab           Turner Construction

Owner:

Cleveland Clinic Foundation

Get a project started

Industrial First played an active role in this 3,000 ton, design assist, OCPTD project as the erector.  This team of contractors, engineers and architects delivered just what the owner was looking for, saving money, and nearly 6 weeks off the erection schedule.